Troutdale Flood Hazard Progress Report

News Release Date
10-16-2019
Back to News

CRS Activity 510

 

Progress Report on Implementation of Credited Plan Date this Report was Prepared: 10/14/2019

Name of Community: City of Troutdale

 

Name of Plan: 2017 Multnomah County Multi-jurisdictional Natural Hazard Mitigation Plan

 

Date of Adoption of Plan: November 29, 2017

 

5 Year CRS Expiration Date: November 29, 2022

 

 

  1. How can a copy of the original plan or area analysis report be obtained:

 

Online - https://www.troutdaleoregon.gov/commdev/page/flood-protection-information and in person at the Community Development Department located at 2200 SW 18th Way, Troutdale, OR 97060.

 

  1. Describe how this evaluation report was prepared and how it was submitted to the governing body, released to the media, and made available to the public:

This report was prepared by Arini Wiryomartono, the city’s Floodplain Manager. The report was submitted to the governing body as a memo, posted in City’s website, a press release to the Media as well as in our Community Development Office and City Hall.

 

 

  1. Provide a description of the implementation of each recommendation or action item in the action plan or area analysis report, including a statement on how the project was implemented or not implemented during the previous year:

Please see attached report.

 

 

  1. Discuss why any objectives were not reached or why implementation is behind schedule: Please see attached report.

 

  1. What are the recommendations for new projects or revised recommendations? Please see attached memo.